Why Data Centers Build Their Own Power: Behind the Meter, Explained

Data centers are building their own power plants because the grid can't connect them fast enough. A large new load can wait five years or more for transmission lines, substations and studies, and an AI data center that sits idle loses money every month. So more of them are putting natural gas turbines or engines on site, behind the meter.
Key takeaways
"Behind the meter" means the power is made on site and used on site. It never runs through the utility's meter.
The driver is time. Grid connections for very large loads can take five years or longer.
Most of the on-site power being planned in the U.S. runs on natural gas, and Texas has the most of it.
Announced isn't built. Only a small share of the plans was under construction as of May 2026.
Why are data centers building their own power plants?
Because waiting for the grid costs more than building a plant. As I put it in a reel last month: "The biggest tech companies in the world have a problem money can't fix fast. The grid. So they stop waiting."
You can build a data center in a year or two. Getting it hooked up to the grid is the slow part. RBC Capital Markets points to interconnection queues spanning five years or longer as the main reason the biggest builders are generating their own power. Texas shows the scale of the line: RBC counted about 356 gigawatts of data center requests waiting on the Texas grid operator as of March 2026. Not all of those will ever be built, but every one of them is asking for power.
What does "behind the meter" mean?
A meter sits where a utility hands electricity to a customer. Anything in front of the meter is the utility's system: power plants, transmission lines, the grid. Anything behind it belongs to the customer.
So behind-the-meter power is a power plant the data center builds next to itself, for itself. In my words from that same reel: "They're building power plants right on site, and it's called behind the meter. The power never touches the grid." Some of these setups stay fully off the grid. Others keep a grid connection as backup, or plan to connect later. The common thread is that the data center doesn't wait for the grid to start running.
On the grid, the wait is the problem. Behind the meter, the data center carries the cost. Rising Phoenix illustration.
Why natural gas?
I'd boil it down to three reasons.
It runs around the clock. AI data centers draw power all day, every day. I said it this way on camera: "every one of them needs power. Around the clock, the day it opens." Gas turbines and engines can run on demand, and they don't depend on the weather.
It's already the biggest fuel on the U.S. grid. EIA's latest outlook has natural gas at about 40% of U.S. electricity generation, and it names data center development as one of the drivers of rising electricity sales.
The equipment is known. Gas turbines and reciprocating engines are proven technology. Builders know how to permit them, finance them and run them.
That doesn't make gas the only answer. Some developers pair it with batteries, solar or a later grid hookup. But for firm power on a short timeline, gas is doing most of the work. "The chips get the headlines. The natural gas does the work." That's the story under the AI story.
How much on-site gas power is actually planned?
A lot is announced. Much less is being built. RBC's May 2026 count:
Stage | Behind-the-meter gas power, U.S. |
|---|---|
Announced | About 101 gigawatts |
With equipment publicly ordered | More than 57 gigawatts |
Under construction | About 7 gigawatts |
Planned in Texas (part of the announced total) | About 38 gigawatts |
For scale, one gigawatt is roughly the output of one large nuclear reactor.
Announced isn't built. Source: RBC Capital Markets, May 14, 2026. Rising Phoenix illustration.
To me, that gap between announced and built is the most honest part of this story. Some of these projects will never happen. Turbine delivery slots, gas supply, permits and local opposition all stand between a press release and a running plant.
Who pays for the power, and why did it become an election issue?
Data centers were on the ballot this year. By early September, campaigns and outside groups had spent more than $45 million on ads mentioning data centers, split almost evenly between the parties. The worry is simple: if the grid has to build new lines and plants to serve a giant new customer, regular homes and businesses might end up sharing the bill.
That pressure points the same direction as the grid wait. As I said after the election: "If you make a data center bring its own power, what does it build? A lot of the time, a natural gas plant, right on site." A behind-the-meter plant is paid for by the data center, not by every other customer on the system.
What are the trade-offs?
Building your own power isn't free, and it isn't simple.
Cost. You're financing your own plant instead of buying power from a utility.
Fuel. You need a reliable gas supply and pipeline space, sometimes for 20 years or more.
Permits and emissions. A gas plant needs air permits, and local rules vary a lot by state and county.
Reliability. With no grid behind you, you carry your own backup.
Risk of overbuilding. Many announced projects may not get built, and demand forecasts for AI can change.
What does this mean for natural gas?
If these plans get built, more gas gets burned close to where it's produced. That's why I watch this so closely as a mineral buyer. The fuel for most of this power comes out of the ground in places like Texas, and royalty owners there get a share of production when gas is sold. I'd rather follow the fuel than try to pick which AI company wins. "I don't have to pick which AI company wins. They all have to keep the lights on." That's an industry trend, not a promise about any one well or any one investment. Gas prices still move, and wells still decline.
If you're new to how mineral and royalty owners get paid, start with mineral rights vs. royalty interests vs. working interests. For the wider menu of ways into energy and real assets, see five routes into oil and gas and our guide to alternatives to the stock market. And if you'd like to talk it through, we're glad to.
Frequently asked questions
What does behind the meter mean for a data center?
It means the data center makes its own electricity on site, usually with natural gas turbines or engines, and uses it directly. The power doesn't flow through the utility's meter or depend on the grid to start running.
Why don't data centers just connect to the grid?
Many do, but connecting a very large new load can take five years or longer while grid operators study it and build new lines and substations. For a company paying for chips and buildings, that wait is expensive.
Is behind-the-meter power always natural gas?
No. Most of what's announced in the U.S. is natural gas, but some projects add batteries, solar, fuel cells or a grid connection later.
Will data centers raise my electric bill?
That depends on the state, the utility and how costs are assigned. Regulators and candidates in both parties are pushing for data centers to pay for what's built to serve them. A behind-the-meter plant is paid for by the data center itself.
How much on-site gas power is being built?
RBC Capital Markets counted about 101 gigawatts announced in the U.S. as of May 2026, more than 57 gigawatts with equipment ordered and about 7 gigawatts under construction.
Jace Graham is a Dallas serial entrepreneur and the founder and CEO of Rising Phoenix Resources, with companies across oil and gas, minerals and royalties, real estate, private lending and energy. His foundation is oil and gas.
For accredited investors only. This is not an offer to sell or a solicitation of an offer to buy securities. Any offer is made solely through the Private Placement Memorandum of the applicable fund, which contains important information about risks, fees, and expenses. Past performance does not guarantee future results.
This article is for education only. It is not investment, tax or legal advice, and it is not an offer to sell or a solicitation of an offer to buy any security. Any offering is made only through its offering documents.